Suppose a factory has 7 sewing line and handling various style.
Line-1
Line-2
Line-3
Line-4
Line-5
Line-6
Line-7
Style
A
B
C
E
F
G
H
SMV
5
10
8.5
4.5
7
18
15
No of Operators
21
25
23
20
19
36
32
No of Helpers
9
10
9
8
11
14
13
Planned Working Hour
8
Planned Efficiency
60%
Available Time
Target = ---------------------------X Planned Efficiency
SMV
Line-1:
Target for 100% Efficiency = (30x8x60) / 5 = 2880 Pcs
Target on 60% Efficiency = [(30x8x60) / 5] x 60% = 1728 Pcs
Line-2:
Target for 100% Efficiency = (35x8x60) / 10 = 1680 Pcs
Target on 60% Efficiency = [(35x8x60) / 10] x 60% = 1008 Pcs
Line-3, 4, 5, 6 & 7:
Same process……
Factory Target for 8 hrs = Line-1+ Line-2+ Line-3+……..+ Line-7