In general Efficiency is the percentage of output to input ratio.
Output or Used Time
Efficiency = ------------------------------- X 100 %
Input or Available Time
Output x SMV
Sewing Efficiency = -------------------- X 100 %
Available Time
Output x SMV
= ----------------------------------------------- X 100 %
Total Used Man x Working Hr x 60
Note: SMV = Time required in min to complete 1 piece body.
|
Line-1 |
Line-2 |
Line-3 |
Line-4 |
Style |
A |
B |
C |
D |
SMV |
5 |
10 |
8.5 |
15 |
No of Operators |
21 |
25 |
23 |
32 |
No of Helpers |
9 |
10 |
9 |
13 |
Output/ Production |
1500 |
1200 |
1400 |
1000 |
Working Hr |
10 |
8 |
10 |
11 |
|
|
|
|
|
Used Time (Min) |
1500x5=7500 |
1200x10=12000 |
1400x8.5=11900 |
1000x15=15000 |
Available Time (Min) |
30x10x60 =18000 |
35x8x60 =16800 |
32x10x60 =19200 |
40x11x60 =26400 |
Line wise Efficiency |
(7500/18000)x100 =41.67% |
(12000/16800)x100 =71.43% |
(11900/19200)x100 =61.98% |
(1500/26400)x100 =56.82% |
(7500+12000+11900+15000)
Factory Efficiency = --------------------------------------- X 100 %
(18000+16800+19200+26400)
= (46400/80400) x 100 %
= 57.71%