How Can You Set Target for a Sewing Line as well as Factory?

How Can You Set Target for a Sewing Line as well as Factory?

 

Suppose a factory has 7 sewing line and handling various style.

 

 

Line-1

Line-2

Line-3

Line-4

Line-5

Line-6

Line-7

Style

A

B

C

E

F

G

H

SMV

5

10

8.5

4.5

7

18

15

No of Operators

21

25

23

20

19

36

32

No of Helpers

9

10

9

8

11

14

13

Planned Working Hour

8

Planned Efficiency

60%

 

 

                 Available Time

Target = ---------------------------X Planned Efficiency

                        SMV

                                    

Line-1:

Target for 100% Efficiency = (30x8x60) / 5 = 2880 Pcs

Target on 60% Efficiency = [(30x8x60) / 5] x 60% = 1728 Pcs

 

Line-2:

Target for 100% Efficiency = (35x8x60) / 10 = 1680 Pcs

Target on 60% Efficiency = [(35x8x60) / 10] x 60% = 1008 Pcs

 

Line-3, 4, 5, 6 & 7:

Same process……                 

 

Factory Target for 8 hrs = Line-1+ Line-2+ Line-3+……..+ Line-7